A project manager seeking insight on previous stakeholder management plans and their effectiveness should evaluate:
A project manager seeking insight on previous stakeholder management plans and their effectiveness should evaluate:
A . Historical information and the lessons-learned database.
B . Historical information and the stakeholder register.
C . Organizational process assets and the lessons-learned database.
D . Project documents and historical information.
Answer: A