A project manager is trying to ensure the quality of the design and reduce the number of potential defects. The project manager would like to use the fishbone diagram to perform this analysis.
A project manager is trying to ensure the quality of the design and reduce the number of potential defects. The project manager would like to use the fishbone diagram to perform this analysis.
This type of modeling relies on:
A . Prioritizing the specific event.
B . Variance in the process over time.
C . Causes of a specific event.
D . Determining the number of events.
Answer: C