A project manager is creating the WBS. In which of the following phases is the project?

A project manager is creating the WBS. In which of the following phases is the project?
A . Initiation
B . Planning
C . Execution
D . Closing

Answer: B

Explanation:

Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 139