A project manager detects low performance from a team member who previously demonstrated to be a highly skilled asset. The team member explains that being part of two teams is too time consuming.

A project manager detects low performance from a team member who previously demonstrated to be a highly skilled asset. The team member explains that being part of two teams is too time consuming.

This is a disadvantage of having:
A . dedicated resources.
B . interproject dependencies.
C . resource overallocation.
D . shared resources.

Answer: D