A project management office (PMO) assigns a resource to a project To what should the project manager refer to evaluate this resource?
A project management office (PMO) assigns a resource to a project To what should the project manager refer to evaluate this resource?
A . Expert judgment
B . Resource requirements
C . Resource management plan
D . Responsible, accountable, consult, and inform (RACI) matrix
Answer: C