A project is typically defined in terms of scope, time, cost and which other parameter?
A project is typically defined in terms of scope, time, cost and which other parameter?
A . Benefits.
B . Quality.
C . Tolerance.
D . Controls.
Answer: D
Latest APM-PFQ Dumps Valid Version with 354 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments