A project is nearing completion when the project manager learns that a change in market regulations may impact the project, what sn6uld the project manager do?
A project is nearing completion when the project manager learns that a change in market regulations may impact the project, what sn6uld the project manager do?
A . Review the risk management plan.
B . Perform a cost-benefit analysis.
C . Check the stakeholder register.
D . Update the cost baseline.
Answer: A