A procurement manager is preparing a long-term contract with a major supplier. She decides to use the variable pricing arrangement using price indices. The payment terms describe the circumstances and mechanism where the price is allowed to change. In order to successfully manage this type of contract, the buying organisation should have…?

A procurement manager is preparing a long-term contract with a major supplier. She decides to use the variable pricing arrangement using price indices. The payment terms describe the circumstances and mechanism where the price is allowed to change. In order to successfully manage this type of contract, the buying organisation should have…?
A . Good market knowledge
B. Selection of base year
C. Value for money
D. Economy of scale

Answer: A

Explanation:

There are several approaches to price adjustment for long-term contract. Describing circumstances and mechanism is one of them. Although this approach has some limitations, it is the best option. It relies on good market knowledge but provides the most equitable approach to satisfying the needs of the purchaser and the supplier.

Reference: CIPS study guide page 184

LO 3, AC 3.3

Latest L4M3 Dumps Valid Version with 193 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments