A large Internet service provider needs to shut down the equipment in the computer room for maintenance in batches. As a cutover project manager, which of the following time points would you prefer?

A large Internet service provider needs to shut down the equipment in the computer room for maintenance in batches. As a cutover project manager, which of the following time points would you prefer?
A . Labor Day
B . National Day
C . Weekend
D . Working Days

Answer: D