A company recently used 500 direct labor hours to manufacture ten units of a new product, if the company employs the cumulative average-time learning model with a 90% learning curve, the number of direct labor hours the company would expect to use to produce the next ten units of this product is
A . 500
B. 475
C. 450
D. 400
Answer: D