A Belt gathered the following defect data for a trouser production line and wanted to assemble it into a Pareto Chart. The correct order from left to right in the chart would be:
Data: Cutting 29
Forming 43
Stitching 17
Sealing 51
A . Sealing, Forming, Cutting, Stitching
B . Cutting, Stitching, Sealing, Forming
C . Stitching, Forming, Cutting, Sealing
D . Forming, Cutting, Sealing, Stitching
Answer: A