A Belt concludes a Lean Six Sigma project with the creation of a Control Plan. At what point can the Control Plan be closed?

A Belt concludes a Lean Six Sigma project with the creation of a Control Plan. At what point can the Control Plan be closed?
A . Never, a Control Plan is a living document
B . As soon as the Champion signs off
C . Within 30 days of the LSS project review team meeting
D . After the project has been presented at the recognition event

Answer: A