____________ is defined as covering work whose component activities are less defined and whose interrelationships are conditional.
____________ is defined as covering work whose component activities are less defined and whose interrelationships are conditional.
A . Soft logic
B . Hard logic
C . Deductive logic
D . Inductive logic
Answer: A
Explanation:
Soft logic refers to the sequencing of project activities that is flexible, based on discretionary decisions about the order of activities. It is used in situations where the component activities are less defined, and the relationships between these activities are conditional rather than strictly dictated by the project’s physical constraints. This approach allows for flexibility in project scheduling, accommodating changes in the sequence of activities without significantly impacting the project’s overall timeline.
For example, if certain tasks can be performed in parallel or in a different sequence without affecting the project outcome, soft logic would apply. This contrasts with hard logic, where activities must occur in a specific order due to the physical or technical constraints of the project.
Latest CCP Dumps Valid Version with 189 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund