__________ shows user how their team is progressing against the work for an epic.
__________ shows user how their team is progressing against the work for an epic.
Cumulative flow diagram
A . Epic burndown report
B. Burndown chart
C. Velocity chart
D. Control chart
Answer: A
Explanation:
The Epic Burndown report shows you how your team is progressing against the work for an epic. An epic is a large user story that can be broken down into a number of smaller stories. The report will show data based on the estimation statistic that your board is using.