Which of the following risk strategies is the project manager applying?
A project manager has contracted a third-party vendor to achieve milestones.
Which of the following risk strategies is the project manager applying?
A . Transfer
B . Accept
C . Avoid
D . Mitigate
Answer: A
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 238