Which object is relevant in assembly processing to create an assembly order for the SD document?
- A . Project profile
- B . Item category
- C . Requirement class
- D . Control key
You want to establish costing for WBS. Costing should be easy to use and should not refer to cost elements.
What method for costing do you use?
- A . Unit costing for WBS
- B . Easy Cost Planning (ECP) for WBS
- C . Detailed planning for WBS
- D . Planning of overall values
You want to use billing for a customer project.
Which customizing object controls the billing of sales order items?
- A . Requirements type
- B . Requirements class
- C . Item category
- D . Schedule line category
Which planning method can prevent further rescheduling of activities?
- A . Partial confirmation of activities
- B . Capacity requirements activation
- C . Capacity levelling
- D . Workforce planning
You want to set up the field selection of the Cross-Application Time Sheet (CATS) in Customizing.
Which influencing field do you use?
- A . Network profile
- B . Data entry profile
- C . Project profile
- D . Network type
You use networks and internal activities in your project. You have activated capacity requirements and notice that one work center is overloaded. You have no authorization to change the work center.
How can you reduce the overload of the work center? Note: There are 2 correct answers to this question
- A . Maintain subordinate internal activity elements assigned to other work centres
- B . Increase the capacities of the work center in the project planning board.
- C . Trigger automatic capacity leveling inside the project planning board
- D . Shift activities backward or forward on the time axis where more capacities are available
Which statements describe planned and actual revenue for WBS elements? Note: There are 2 correct answers to this question
- A . Planned revenue requires a sales order assigned to a WBS element
- B . Planned revenue can be transferred from a sales quotation
- C . Actual revenue is posted via a billing plan assigned to a WBS element
- D . Actual revenue is posted via a billing document created from a sales order
A service company uses project management and they complain that the system does not prevent
their project managers from exceeding their budgets.
What actions do you have to take to solve the problem?
- A . Activate availability control for the WBS elements. Define the tolerance limits on each WBS element
- B . Activate availability control in the assigned budget profile. Define the tolerance limits in customizing
- C . Activate commitment management in the project definition Enter the budget in the master data of the top WBS element
- D . Activate availability control for projects in the controlling area. Enter the plan data for each WBS element
Which of the following statements apply to project versions? Note: There are 2 correct answers to this question
- A . Project versions can be changed
- B . Project versions are mandatory for Milestone Trend Analysis (MTA)
- C . Project versions can be created automatically based on user status
- D . Manually Created project versions always require a project version profile
You want to make sure that certain tasks must start on a given date. Where can you maintain constraints for start dates?
- A . Activity
- B . Network header
- C . Milestone
- D . Activity element