Which of the following would; the auditor most likely use to measure the project team’s performance related to how project tasks are completed?
An internal auditor is reviewing key phases of a software development project.
Which of the following would; the auditor most likely use to measure the project team’s performance related to how project tasks are completed?
A . A balanced scorecard.
B . A quality audit
C . Earned value analysis.
D . Trend analysis
Answer: B