What should the project manager do next?
Team members are having a discussion with the project manager In the last retrospective meeting, the team realized that the obsolete equipment could affect the next iteration of the project. The team recommends buying new equipment because it is critical to the success of the final deliverable
What should the project manager do next?
A . Check the project budget to verify if there is enough contingency reserve
B . Review the cost management plan to determine how to address this issue
C . Tell the team members that more equipment is not part of the project’s scope.
D . Submit a change request to increase the budget and buy new equipment
Answer: A