What are the prerequisites to generate project stock reservations?

A component is assigned to a network activity.

What are the prerequisites to generate project stock reservations? Note: There are 3 correct answers to this question
A . The network activity is assigned to a WBS element
B . The network is assigned to a sales order item
C . The material master of the component must permit project stock management
D . The Project Stock indicator is set in the project definition (non-valuated or valuated)
E . A procurement indicator must be assigned to the activity

Answer: A,C,D