Which objects do you have to maintain to enable automatic assignment of material components to the project? Note: There are 2 correct answers to this question

Which objects do you have to maintain to enable automatic assignment of material components to the project? Note: There are 2 correct answers to this question
A . Material master
B . Network activity
C . WBS element
D . BOM item

Answer: B,D