You want to make sure that certain tasks must start on a given date. Where can you maintain constraints for start dates?
You want to make sure that certain tasks must start on a given date. Where can you maintain constraints for start dates?
A . Activity
B . Network header
C . Milestone
D . Activity element
Answer: A