Which of the following is described in this scenario?
During a project, a key stakeholder asks a project team member to add a requirement. The team member adds the requirement without informing the project manager.
Which of the following is described in this scenario?
A . Change request
B . Risk mitigation
C . Change control
D . Scope creep
Answer: D