For which type of deployment should the administrator plan while confirming resource capacity?
An administrator is preparing to deploy vRealize Automation into production in one of several geo-distributed datacenters.
For which type of deployment should the administrator plan while confirming resource capacity? (Choose the best answer.)
A . Standard
B . Multi-site
C . Distributed
D . Clustered
Answer: D