Does the solution meet the goal?

Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution.

After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.

A company implements Dynamics 365 for Finance and Operations for their Lean manufacturing environment.

There has been an engineering change to a fixed quantity product that is in production. This change will add an additional processing step as the second step. The existing version must be phased out and replaced by the new version.

You need to ensure that the engineering change takes affect at the end of the month.

Solution:

• Add a new version to the existing production flow. Set the expiration date to the end of the month.

• Create an activity for the new process step and add it in the proper sequence.

• Create a Kanban rule that incorporates the new activity. Set the expiration date to the end of the month.

• Edit the existing Kanban rule. Set the expiration date to the end of the month. Specify the new Kanban rule as the replacement rule.

Does the solution meet the goal?
A . Yes
B . No

Answer: B