CORRECT TEXT
CORRECT TEXT
You are a functional consultant for Contoso Entertainment System USA (USMF).
You need to schedule the Material Requirements Planning (MRP) master plan to run nightly at 03:00 (UTC-8).
To complete this task, sign in to Dynamics 365 portal.
Answer: You need to configure a batch job to run the master plan nightly.
Create the batch job
✑ Go to Navigation pane > Modules > System administration > Inquiries > Batch jobs.
✑ Click New.
✑ In the Job description field, type a value.
✑ In the Scheduled start date/time field, enter a date and time.
✑ Click Save.
Create a recurrence
✑ On the Action Pane, click Batch job.
✑ Click Recurrence. Use these options to enter a range and pattern for the recurrence.
✑ Click OK.