You are a functional consultant for Contoso Entertainment System USA (USMF).

You need to schedule the Material Requirements Planning (MRP) master plan to run nightly at 03:00 (UTC-8).

To complete this task, sign in to Dynamics 365 portal.

Answer: You need to configure a batch job to run the master plan nightly.

Create the batch job

✑ Go to Navigation pane > Modules > System administration > Inquiries > Batch jobs.

✑ Click New.

✑ In the Job description field, type a value.

✑ In the Scheduled start date/time field, enter a date and time.

✑ Click Save.

Create a recurrence

✑ On the Action Pane, click Batch job.

✑ Click Recurrence. Use these options to enter a range and pattern for the recurrence.

✑ Click OK.