Which two of the listed statements are business requirements?
During a transformation project kick-off meeting, an architect highlights specific areas on which to focus while developing the new conceptual design.
Which two of the listed statements are business requirements? (Choose two.)
A . The project should use the existing storage devices within the data center
B . Sites must support a network latency of less than 12 ms round-trip time (RTT)
C . The solution must allow data replication between sites
D . There is no budget specifically assigned for disaster recovery
E . There must not be a single point of failure for the virtual infrastructure
Answer: C,E