Which of the following statements regarding program change management is not correct?

Which of the following statements regarding program change management is not correct?
A . The goal of the change management process is to sustain and improve organizational operations.
B . The degree of risk associated with a proposed change determines if the change request requires authorization.
C . In order to protect the production environment, changes must be managed in a repeatable, defined, and predictable manner.
D . All changes should be tested in a non-production environment before migrating to the production environment.

Answer: B