Your project requires confirmation of sales order quantities for certain materialseven if the stock of those materials is currently below the safe y stock level. Where do you configure this? Choose the correct answer.

Your project requires confirmation of sales order quantities for certain materialseven if the stock of those materials is currently below the safe y stock level. Where do you configure this? Choose the correct answer.
A . The Special Stock indicator in the Item category
B . The Item Category group in the material master
C . The Checking rule at transaction level
D . The scope of the availability check

Answer: D