Which of the following roles approves the project scope statement, phase gate reviews, solution validations, scope changes, and project success criteria?

Which of the following roles approves the project scope statement, phase gate reviews, solution validations, scope changes, and project success criteria?
A . Project manager
B . Subject matter expert
C . Solution owner
D . Stakeholder

Answer: A