Which stakeholders were missed in the requirements?

A business analyst (BA) was tasked with eliciting requirements for a new product scheduling system. The BA interviewed and discussed the requirements with the manager and Supervisor. The requirements were written and approved by both the supervise and manager .

Which stakeholders were missed in the requirements?
A . End users
B . Project manager
C . Upper management
D . IT support

Answer: A