During the testing phase, a new requirement surfaced and the stakeholder asked the developer to modify the code without informing the Business analyst (BA). The BA became aware of the new functionality after a defect was raised against another component of the design.
During the testing phase, a new requirement surfaced and the stakeholder asked the developer to modify the code without informing the Business analyst (BA). The BA became aware of the new functionality after a defect was raised against another component of the design.
The BA can keep this situation from occurring in the future by creating a:
A . risk strategy.
B . prioritization approach.
C . change control process.
D . stakeholder engagement plan.
Answer: C