Which settings do you make to achieve this?

You want to set up a make-to-order planning scenario for a finished material. Some components from the bill of materials (BOM) should be procured per sales order, other components should be procured for various requirements. Fore casting is NOT possible .

Which settings do you make to achieve this?
A . Planning strategy 50 (Planning without final assembly) and the corresponding Mixed MRP indicator
B . Planning strategy 20 (Make-to-Order) and the corresponding individual Collective indicator
C . Planning strategy 20 (Make-to-Order) and the corresponding Mixed MRP indicator
D . Planning strategy 50 (Planning without final assembly) and the corresponding individual Collective Indicator.

Answer: D