Which of the following elements does MRP take into account during net requirement calculation? Note: There are 2 correct answers to this question.

Which of the following elements does MRP take into account during net requirement calculation? Note: There are 2 correct answers to this question.
A . Maximum stock level
B . Purchase orders
C . Safety stock
D . Lot size

Answer: C,D