Which planning strategy supports the consumption of planned independent requirements for the semi-finished material?
You want to triggering-house production of a semi-finished mater al before a sales order for the corresponding finished good is received .
Which planning strategy supports the consumption of planned independent requirements for the semi-finished material?
A . Make-to-order production (20)
B . Planning without final assembly (50)
C . Planning with final assembly (40)
D . Planning at assembly level (70)
Answer: B