Which of the following is the best practice for testing a Business Continuity Plan (BCP)?

Which of the following is the best practice for testing a Business Continuity Plan (BCP)?
A . Test before the IT Audit
B . Test when environment changes
C . Test after installation of security patches
D . Test after implementation of system patches

Answer: B