What should the project manager do?
An agile project is running its second of six iterations. One new team member who does not have agile experience has just joined the team. In the daily meetings, the project manager observes that the team is having problems meeting their goals.
What should the project manager do?
A . Provide feedback to the team and conduct a meeting to review the team rules.
B . Provide feedback to the team and conduct a retrospective meeting to find a root cause.
C . Provide feedback to the team and request agile training for the new member.
D . Provide feedback to the team and coach the new team member in agile methodology.
Answer: B