What should the project manager do to improve the stakeholder’s engagement?
During the initiating phase of a project, a key stakeholder requests frequent changes to the project scope.
What should the project manager do to improve the stakeholder’s engagement?
A . Discuss the work breakdown structure (WBS) with the key stakeholder and refine the requirements
B . Update the project backlog and discuss it with the key stakeholder
C . Update the project charter and discuss it with the key stakeholder.
D . Discuss the project scope statement with the key stakeholder and build prototypes
Answer: D