What should the project manager do?
During the executing phase, a project manager is reviewing the issue log and finds there are outstanding high-priority issues that are still open. Most of the open issues require effort from external domain experts who are not on the project team.
What should the project manager do?
A . Ask the issue reporter to close the issues, because there are no project team members who have the required domain knowledge.
B . Review the open issues with the issue reporter and issue a change request to hire an external domain expert.
C . Request that the project team members learn the required domain knowledge and resolve the open issues in a short time.
D . Reduce the project scope to ensure that the project team has the knowledge to deliver the system on schedule.
Answer: B
Latest PMP Dumps Valid Version with 721 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund