Which THREE activities would be valid steps during the development of the test strategy?2 credits (2 out of 3 correct 1 credit)

Which THREE activities would be valid steps during the development of the test strategy?2 credits (2 out of 3 correct 1 credit)
A . Identify test staff members that will be involved in the system test
B . Define test career paths
C . Understand the software development life cycle used by the software house
D . Assess the testing that needs to be done to minimize the risks
E . Issue the test strategy document for review
F . Define a master test plan template
G . Perform a project risk analysis

Answer: C,D,E