Which statement best describes the Sprint Backlog as outcome of the Sprint Planning?

Which statement best describes the Sprint Backlog as outcome of the Sprint Planning?
A . It is a complete list of all work to be done in a Sprint.
B . Every item has a designated owner.
C . Each task is estimated in hours.
D . It is the Development Team’s plan for the Sprint.
E . It is ordered by the Product Owner.

Answer: D

Latest PSM I Dumps Valid Version with 197 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments