What activities would a Product Owner typically undertake in the phase between the end of the current Sprint and the start of the next Sprint?

What activities would a Product Owner typically undertake in the phase between the end of the current Sprint and the start of the next Sprint?
A . There are no such activities. The next Sprint starts immediately after the current Sprint.
B . Refine the Product Backlog.
C . Work with the Quality Assurance departments on the Increment of the current Sprint.
D . Update the project plan with stakeholders.

Answer: A