What factors likely led to this?

At the seventh Sprint Review, the stakeholders are disappointed and angry. They have determined that the product or system being built will not meet their needs and will cost more than they are willing to spend.

What factors likely led to this? (Choose two.)
A . The Project Management Office (PMO) has not been engaged adequately.
B . The Product Owner has not been keeping the stakeholders aware of the progress of the project.
C . The stakeholders haven’t been using the Sprint Reviews to inspect and evaluate progress.
D . The stakeholders were not allowed to enter the development area.

Answer: A,B

Latest PSM I Dumps Valid Version with 197 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
3 Comments
Inline Feedbacks
View all comments
bonieta sievers
bonieta sievers
2 years ago

also had b and c ,

Safaa
Safaa
3 years ago

Answer is B & C PMO has no role in the Scrum framework

Sal
Sal
3 years ago

The Project Management Office is not defined in the Scrum process. The answers are: B,C