What should the project manager do first?
The team architect resigned from the company. The new architect points out a design flaw during a planning meeting that may potentially impact the final quality.
What should the project manager do first?
A . Review the scope management plan.
B . Update the design with changes.
C . Request an architecture review.
D . Update the quality management plan
Answer: C
Latest PMP Dumps Valid Version with 721 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments