What management decision is suited for this situation?

A self-organizing team was delivering as committed. The team accepted a development task with new technology and the iterations started to have reduced velocity.

What management decision is suited for this situation?
A . Provide opportunity for team members to learn and adjust to the technology.
B . Move team members who are not performing from the team.
C . Add new members to the team and increase the velocity
D . Re-assign the project to a team that has worked with this technology

Answer: A