What two actions should the project manager take?
An agile project is in its sixth iteration out of 10 After the iteration review, the team receives feedback from the stakeholders that could result in a change in the product.
What two actions should the project manager take? (Choose two)
A . Ask the stakeholders about the priority of this change
B . Ask the product owner to review the product backlog
C . Ask the team members to analyze the impact of this change
D . Ask the sponsor to approve the change request
E . Ask the team members to include the change in the next iteration
Answer: A,B