Which of the following document is created first after project is awarded and statement of work is handed over to the project manager?
Which of the following document is created first after project is awarded and statement of work is handed over to the project manager?
A . Work breakdown structure (WBS)
B . WBS dictionary
C . Project scope statement
D . Project charter
Answer: D