Because of the ongoing and iterative nature of portfolio management, the processes in it are continually repeated as new components are added, and others are completed or terminated. Revisions are constant given complexity, risks, and the rate of change.

Because of the ongoing and iterative nature of portfolio management, the processes in it are continually repeated as new components are added, and others are completed or terminated. Revisions are constant given complexity, risks, and the rate of change.

As you work to optimize the portfolio, it is helpful to:
A . Assign components to predefined categories
B . Prepare a flowchart
C . Organize ideas from stakeholders into logical groupings
D . Perform a structure analysis of roles and responsibilities

Answer: B