When it relates to developing the performance management plan, what is the purpose of using this analysis?

A portfolio manager needs to continuously balance the need and requirements with the available resources and needs to maintain a balanced portfolio and portfolio resources in order to optimize delivery. Capability and Capacity analysis is performed in 4 of the portfolio management processes and it serves a slightly different purpose in each and every one of them.

When it relates to developing the performance management plan, what is the purpose of using this analysis?
A . Performed to understand the human, financial, and asset capacity and capability of the organization in order to select, fund, and execute portfolio components
B . To study the capability of resources, match them against the portfolio’s objectives and goals, and translate the capability into what capacity is possible to meet the portfolio demands
C . To understand how much work is able to be performed based on the resources available (capacity), as well as the ability of the organization to source and execute the selected portfolio
D . It enables the organization to achieve maximum portfolio benefits given current resource constraints

Answer: A