- All Exams Instant Download
Which of the following capability and capacity analysis is used to just limit the number of components the organization can execute?
You are managing a portfolio in a functional organization and resources are shared between operations and projects. You are continuously performing capability and capacity analysis in order to optimize the portfolio .
Which of the following capability and capacity analysis is used to just limit the number of components the organization can execute?
A . Knowledge Basis
B . Financial
C . Human Resources
D . Assets
Answer: C
Latest PfMP Dumps Valid Version with 495 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments