Which of the following should be put in place when negotiating with a new vendor about the timeliness of the response to a significant outage or incident?
Which of the following should be put in place when negotiating with a new vendor about the timeliness of the response to a significant outage or incident?
A . MOU
B . MTTR
C . SLA
D . NDA
Answer: C